Project Description
Pocono Mountain Corporate Center West Lagoon / Spray Irrigation Project
Project Overview
Design of 50,000 gpd wastewater treatment lagoon with disposal by spray irrigation. The project consists of a single aerated lagoon containing three cells which are created by floating baffles. The lagoon contains a volclay liner to protect the groundwater and the effluent is applied to a 26.4 acre, three zone wooded spray field.
Project Details
The project included:
- Wastewater Treatment: 50,000 gallon per day wastewater treatment;
- Wastewater Containment: Wastewater Treatment Lagoons;
- Water Reuse: Spray Irrigation Land Application on 26 acres;
- Three zone wooded spray irrigation included in project;
Recognition / Awards
This project was recognized at both the local and state levels for it’s dedication to sustainable growth and innovative community-based wastewater design.
Customer
Pocono Mountain Industrial Park Authority
Location
Project Type
Decentralized Wastewater Treatment Facility
Project Dates
2010
Project Cost
$1.85 Million
Project Participants and Roles
Owner
Pocono Mountain Industrial Park Authority
Wastewater Lagoon / Spray Irrigation Design Engineer
Castle Valley Consultants, Inc
Authority Engineer / Site Design
Niclaus Engineering Corporation